The main pipeline of Saudi Arabia’s recycled water...

2020-12-15 中國石化新聞網

The main pipeline of Saudi agriculture ministry’s recycled water transmission project for irrigation, constructed by Sinopec, was put into operation on August 9, 20 days ahead of the original target date.

The pipeline has a total length of 183.87 km, as a part of Saudi agriculture ministry’s largest water recycling project.

 

沙特最大水循環工程主線投產成功

  8月10日,由中原油建承建的沙特農業部淨化水輸水灌溉工程主幹線一次性投產成功,比原定投產日期提前20天。

  據了解,該工程為沙特農業部歷史上最大的水循環再利用項目,管道總長183.87公裡。(李 振)