Multi-hazard risk assessment 多災害風險評估 1.1

2021-02-26 安廈系統科技


1.6 Resulting flood risks on the national and provincial level

Table 1-5 and Figures 1-9 – 1-12 show, at the national and district levels, the economic losses and affected people in absolute numbers, as well as in percentages of the total population and total capital stock.


1.7 Projection of future flood risk

The information from the SSP (Shared Socio-Economic Pathway) scenarios developed for the Intergovernmental Panel on Climate Change (IPCC) is used to determine the projections of exposed asset values. According to the SSP projections, the flood risk in Afghanistan will increase substantially, as more of the population will be exposed to flooding, and more and more valuable assets are accumulating. In Figures 1-13 and 1-14, the expected annual people affected by flooding, and the expected annual damages from flooding in Afghanistan until the year 2050 are displayed. Note that these figures are based on the future climate scenario simulated by the NorESM GCM (as described in section 1.3.3).


1.8 Measures for resilient reconstruction and risk reduction

1.8.1 Introduction

If the level of flood risk is not acceptable, flood risk reduction is necessary. Several measures can be taken to reduce flood risks, from measures that focus on load reduction (e.g., upstream measures), prevention with dikes, reduction of consequences, or compensation through insurance; see Figure 1-15 for an overview.

Following the definition of risk as a function of probabilities and consequences of a set of scenarios, two types of interventions can be distinguished: those that reduce the probability of flooding (prevention) or those that reduce the consequences (mitigation).

Prevention measures reduce the probability of flooding. They include reducing the loads on a flood defense (e.g., room for rivers or foreshores for wave reduction) or increasing the strength of the flood defense (dike reinforcement).

Mitigation measures reduce the consequences of failure of a flood defense. Examples of mitigation measures include: adaptation of existing or new buildings, the construction of internal compartment dikes to limit the flooded area, and emergency and evacuation plans. A special category of measures concerns insurance or government compensation as it will not reduce the damage from flooding, but instead leads to compensation or redistribution after damage has occurred. 

• Several frameworks have been developed for managing flood risks and evaluating portfolios of flood risk reduction measures. Many of these frameworks attempt to combine the different risk reduction measures and the various actors involved. Eventually, all the different interventions can also be expressed by means of their contributions to the reduction of flooding probability or flooding consequences, and thus be evaluated for risk reduction and cost-effectiveness.

• For example, the 「multilayer safety」 approach (depicted in Figure 1-16) distinguishes prevention as a first layer, land use planning as a second layer, and emergency management as a third layer.

1.8.2 Types of flood prevention measures

Flood defenses are generally a useful measure to prevent flooding of low-lying areas. A flood defense is a hydraulic structure with the primary objective to provide protection against flooding along the coast, rivers, lakes, and other waterways. Different types of flood defenses exist. The most important ones are:

• A dike (levee) is a water retaining structure consisting of soil, with a sufficient elevation and strength to be able to retain the water under extreme circumstances.

• A dam is another type of water retaining structure which separates two water bodies. 

• A flood wall is a water retaining structure which generally consists of concrete, and sometimes steel. Due to the high horizontal forces on the flood wall, a solid foundation is necessary. 

Temporary flood defenses are used during periods of high water levels to strengthen dikes or other vulnerable objects. Examples of temporary flood defenses are sandbags, synthetic-bellow barriers, or box barriers that are filled with water for the purpose of stability, and various types of beams and stop logs.

• Hydraulic structures, such as sluices, siphons, and pumping stations arestructures that can also be a part of a flood defense system.


1.9 Flood risk, erosion, and cost-benefit analysis for focus areas

1.9.1 Introduction on Cost-Benefit Analysis 

A Cost-Benefit Analysis (CBA) on flood risk reduction measures is conducted to select the most economically feasible measures. In a CBA the costs, i.e., the investments of a set of measures, is compared with the reduction in flood damages from the proposed measures. When benefits outweigh the costs, a flood risk reduction measure is deemed economically viable. For the examples that are described in this report, we have chosen measures that are effective for frequent flood events (i.e., those with a relative short return period of 1 in 20 years), which are associated with less extensive flooding in order to limit complexity of the designs of the flood risk reduction measures. 

The CBA is based on an analysis over a period of 20 years, and assumes an average economic growth of 7 percent, which is the average economic growth over the past 10 years in Afghanistan, as calculated from the world development index database from the World Bank. The result of the cost benefit analysis is presented as the internal rate of return (IRR) on investments in flood risk reduction, based on initial investments (costs) and avoided damages (benefits). Normally a project is considered economically viable when the IRR is equal or higher to the market interest rate.

In order to conduct a CBA for flood risk reduction measures, vulnerability, or potential damages from flood events with specific return periods, need to be determined. In the design for flood risk reduction measures, the new protection level and resulting reduction in potential flood risk is calculated. Estimates of reductions in flood damages are based on the developed hydrological and hydraulic flood hazard estimates (see sections 1.3 and 1.4), and the results from the flood damage FIAT model (section 1.5) that have been developed within the project. The risk reduction and the investment costs and service life of the risk reduction measures are subsequently compared in the CBA. The annual reduction in flood risk is discounted over the timeframe of the project in order to determine the IRR (see above). When IRR reaches a predetermined value a project is deemed economically viable. 

1.9.2 Unit costs

Unit costs for specific flood protection designs are commonly calculated on the basis of total direct construction costs based on material cost and labor and adding surcharges for specific activities, such as planning, detailed designs, supervision, implementation risks, and so on. 

For this study the distinction is made between simple and complex construction based on the following characteristics:

• Simple constructions (small earthworks, small masonry structures, mass concrete, rural environment)• Complex constructions (gabion structures, reinforced concrete structures, large earthworks, urban environment)

Besides flood protection measures such as dams and dikes, the potential reduction of flood damages through adjustments in buildings is assessed. The flood proofing of residential buildings is assumed to be done by either:

• Cement plaster of unfired brick houses; or• Construction of a concrete protection wall around the dwellings.

The cost-benefit analysis and economic rationale for risk reduction measures is illustrated in two study areas:

1. Kabul city flood risk.2. Amu Darya (Panj Aumur) flood risk.

For these case studies, typical risk reduction measures are proposed based on a cost calculation. 

1.9.3 Kabul city case study

1.9.3.1 Model runs for stochastic events

A hydrodynamic model was set up to simulate flooding in the Kabul area. Stochastic events were simulated for the Kabul and Paghman rivers for return periods of 5, 10, 20, 50, 100, 250, 500 and 1,000 years. 

The maximum water depth for a 10-year event resulting from the model is shown in Figure 1-17. First flooding occurs near the confluence of Kabul and Paghman rivers and in the old town located in District 1. 

Figure 1-18 displays the maximum water depth modelled for a 1,000-year event. The flood plain extent is much wider compared to the 10-year event; especially the area near the confluence of Kabul and Paghman rivers is heavily flooded.

The modelled maximum water depths are input for the flood risk analysis for Kabul city. 

1.9.3.2 Impact and flood risk assessment for Kabul

Two options for flood risk management in the Kabul city center are evaluated: 

(i) flood wall strengthening and

(ii) retrofitting of residential buildings through flood proofing. The reconstruction cost for buildings was estimated to be $160/m2. The maximum damage for commercial property was set to $133/m2. 

The analysis was carried out for three different situations:

• S1: Baseline scenario—situation as currently implemented• S2: Dike strengthening—increasing the bank level by 1 meter• S3: Retrofitting—Dry-proofing of residential buildings in the most affected part of District 1, North of Maiwand Street.

1.9.3.3 Risk reduction measures


Dike strengthening 

The embankment level is set at 1,800.5 meters, which is an average of 1 meter above the current level of the river bank protection. The model simulations indicate a flood defense with that level prevents flooding of the old town area up to and including a 50-year event. Figure 1-19 and Figure 1-20 show the resulting maximum water depth for a 10-year event and a 1,000-year event. Dike strengthening prevents flooding of the old town for the 10-year event (compare Figure 1-19 with Figure 1-17), but has a minor effect for the 1,000-year event (compare Figure 1-20 with Figure 1-18).

Table 1-6 shows the results of the baseline situation (no measures) S1, compared to the outcomes of measures for S2 and S3. It can be seen that strategy S2 can lead to a significant decrease of flood damages for both residential and commercial buildings. For flood events less frequent than 1 in 100 years, the effect of the embankment is limited.

Retrofitting buildings

The reduction in flood losses after retrofitting residential buildings is less significant for events up to 1 in 100 years, but still has an effect for floods with lower return periods. 

1.9.3.4 Cost estimate for risk reduction measures

Flood wall strengthening 

Increasing the flood retaining wall within Kabul by 0.5–1 meter over a length of about 600 meters in order to avoid a flood event with a 1 in 50 frequency results in a total cost including flood wall, concrete, and road work of US$398,549. The resulting IRR would be 138 percent, indicating a very positive economic return for investments for flood prevention in Kabul city at this particular location.

Retrofitting buildings

Flood proofing can be achieved by construction of a small concrete/stone wall around a housing compound, or plastering of the lower part of residential buildings (especially mud brick houses) with water proofed cement plaster. Both measures are assumed to have similar costs per protected house.

The cost-benefit analysis is conducted for all houses in Kabul that are exposed to a 1 in 50 years flooding area (with a combined surface of 94,234 m2 residential houses). Total costs for flood proofing of the residential houses are based on the surface of the exposed residential housing to flooding. Implementation of flood proofing results in avoided annual damages of US$341,000. This gives an IRR of 10 percent. The construction of a flood wall, with an IRR of 138 percent, indicates the latter is a far better flood risk reduction measure.

1.9.4 Panj Amur case study


1.9.4.1 Introduction

In order to gain insight into the possibility and economic rationale for the construction of flood risk prevention, a case study was conducted in the Panj Amur catchment area. Based on the risk maps, several areas with significant damages were selected. The areas and the geographic representation of the damages are presented in Figure 1-21, Figure 1-22, and Figure 1-23. The estimated actual damages for different return periods and consequential values of the expected annual damages (EAD) are presented in Table 1-7.

1.9.4.2 Cost benefit of risk reduction measures

Kunduz agricultural area

From the flood hazard maps it has been estimated that for the protection of the agricultural lands in Kunduz (Figure 1-21) approximately 35 km of dike are required. Construction of a simple earth dike would cost about US$3.2 million. This measure, assuming a protection level up to and including the 1 in 20 years flood level, would result in benefits of annual reduced damages of about US$301,000. The IRR of the reduction in annual damages, assuming a lifespan of 20 years of the investment and economic growth of 7 percent, would be 14 percent, showing a significant return of the investment in flood reduction measures.

Puli KhumriFrom 

the map of the Puli Khumri area (Figure 1-22) it can be estimated that a protective embankment of 22 km (2 sides of 11 km each) would be required. Assuming that the embankment will require a stone protection, the construction costs would be US$990,000.

Assuming a protection level up to and including the 1 in 20 years flood level, benefits would result in annual reduced damages of US$223,000. The IRR of the reduction in annual damages, assuming a lifespan of 20 years of the investment and economic growth of 7 percent, would be 29 percent.

Fayzabad

From the map of the Fayazabad area, (Figure 1-23) it can be estimated that a protective embankment of 6 km (2 sides of 3 km each) would be required. As the proposed embankment is in an urban environment, it is assumed that a more complex construction4 in reinforced concrete would be required. Construction costs would be US$1.3 million.

Assuming a protection level up to and including the 1 in 20 years flood level, benefits would result in annual reduced damages of US$112,500. The IRR of the reduction in annual damages, assuming a lifespan of 20 years of the investment and economic growth of 7 percent, would be 12 percent. 

1.9.5 Conclusions from Kabul and Panj Amur case studies

From the calculated flood damages and possible solutions for flood prevention measures, it is clear that urban environments have much higher flood damages. Therefore, as a risk reduction option flood prevention measures have much higher benefits (through avoided damages) in urban areas than in rural areas, including a higher internal rate of return (IRR). The case study of Kabul indicates that there are substantial damages (US$14 million) in a relatively small area (600 m long wall flood). Although the total damages in the rural Panj Amur cases are similar (around US$9 million) the stretches of dike that need reinforcement are longer (up to 35 km length). Nevertheless, flood risk reductions seem economically feasible in all case studies.

The study from Kabul shows that prevention measures are not required along the full length of the proposed embankments, and that flood proofing of houses has a much lower IRR than construction of a flood retaining wall.

Further recommendations include the following:

• For any flood prevention projects, detailed information on local costs (including transport, labor, etc.) is essential to inform the level of protection and type of implementation that would be economically justified.• More information on topography, hydraulic characteristics, subsoil, etc. would better determine the required design of the local flood prevention measures, improving the estimates for costs of construction and materials.

The results presented above provide an initial basis for informed decision making on planning and implementing flood protection measures in Afghanistan, based on a financial cost-benefit analysis. A more extended analysis, including indirect costs because of business interruption and other co-benefits of flood projection, such as prevention of injury, ecological impacts, and so on, could allow a social cost benefit analysis.

相關焦點

  • PIC/S發布《質量風險管理實施的評估》(中英文對照翻譯)
    The quality risk management system should ensure that:質量風險管理是評估、控制、溝通和審查藥品質量風險的系統過程。它既可以主動應用, 也可以追溯應用。
  • 【安全】國際癌症研究機構科學家重申草甘膦致癌風險
    而今年5月份,聯合國糧食與農業組織(FAO)和世界衛生組織(WHO)的另一監管機構聯合發表了一份報告,指出草甘膦成分「不太可能通過飲食導致人類患癌風險增加」。 歐洲新聞主持人採訪中問到,作為普通民眾,WHO 哪個研究機構的報告更為可信?
  • 環境風險評估注意事項
    一、環境風險評估項目:水稻:水生生態系統、鳥類、蜜蜂、家蠶、地下水、非靶標節肢動物。
  • 環境風險評估減免情況介紹
    環境風險評估是指在農藥實際應用條件下,就農藥使用對生態環境產生不良效應的潛在風險和程度進行科學評估。環境風險評估的項目包括水生生態系統、鳥類、蜜蜂、家蠶、地下水、非靶標節肢動物、土壤生物共七項。《農藥登記資料要求》中,農藥製劑分為化學製劑、生化製劑、微生物製劑、植物源製劑四類,其中僅化學製劑需要提交環境風險評估資料,生化製劑、微生物製劑、植物源製劑不需要補充環境風險評估。環境風險評估項目根據製劑需要進行的環境試驗項目不同,可以減免部分項目。
  • 市應急局多舉措增強水旱災害防救能力
    為切實提升全市水旱災害防救能力,今年來,市應急局堅持關口前移,源頭治理,從源頭上減少水旱災害發生的風險,最大限度保護人民群眾的生命和財產安全。
  • 佛山發布地質災害氣象風險3級預警!
    今日12時39分,佛山市自然資源局和市氣象局聯合發布地質災害氣象風險預警:預計8月1日12時-8月2日12時,禪城區的南莊鎮;南海區的西樵鎮,裏水鎮,獅山鎮,桂城街道;順德區的大良街道,均安鎮,龍江鎮,容桂街道,勒流街道,杏壇鎮;三水區的雲東海街道,白坭鎮,
  • 吳中區第一次全國自然災害綜合風險普查工作方案(徵求意見稿)!
    一是首次聚合絕大多數涉災行業部門協同開展普查,探索建立多部門協同普查的長效工作機制,這也是切實改變傳統的「九龍治水」,解決部門數據共享壁壘的具體行動。二是首次實現自然災害風險要素的「全集」調查。本次普查既涉及多個自然災害類型的致災要素調查,也涉及房屋建築、交通設施等重要承災體要素的調查,還涉及歷史災害、綜合減災資源(能力)的調查,這些工作與以往開展的單要素、單部門、部分地區的調查有明顯不同。三是首次實現不同行業部門採用統一的技術框架開展風險評估工作。
  • 上任第三天,拜登下令對美國「國內極端主義」風險做全面評估
    據路透社報導,白宮新聞秘書珍·普薩基當地時間1月22日在簡報會上表示,美國總統拜登指示其政府對美國國內的極端主義風險進行全面評估。拜登資料圖報導稱,普薩基表示,評估將由美國國家情報總監辦公室、聯邦調查局(FBI)及國土安全部協調進行。普薩基告訴記者:「我們需要基於事實的分析,在此基礎上我們可以制定政策。」
  • 搞定澳洲技術移民第一步:職業評估(澳大利亞各職業評估機構的基本要求及審批周期介紹)
    1. 澳大利亞各職業評估機構的基本要求及審批周期介紹:ACS: Australian Computer Society基本要求:(滿足一下情況中的任意一種)· 澳洲 IT學士或學士以上學位+ 1年以上相關工作經驗或完成PY職業年;· 境外IT專業學士或以上+至少2年以上相關工作經驗
  • 近期雨量增大,地質災害發生危險高,這些地方需要重點防範!
    關於全面排查地質災害隱患點的緊急通知入汛以來,黑龍江省出現了多次較大降雨過程,土壤含水量已經飽和,地質災害發生風險高。為此,黑龍江省應急管理廳下發緊急通知,要求全面排查地質災害隱患點。敲黑板!!!需要重點防範的地點是:牡丹江市、佳木斯市、雞西市、雙鴨山市、七臺河市、鶴崗市。
  • 體能資訊|客戶動作模式評估
    Clinical biomechanical studies on ACL injury risk factors. Strength and Conditioning Journal 31(1): 76-85, 2009.Numata, H, Nakase, J, Kitaoka, K, Shima, Y, Oshima, T,Takata, Y, et al.
  • 【頭條】文縣暴洪災害造成1人死亡8人失聯
    2017年8月6日晚22時至8月7日早晨7時,文縣天池鎮、梨坪鎮、舍書鄉出現強降水天氣,引發暴洪泥石流等災害,造成天池、梨坪、舍書3個鄉鎮不同程度受災。經初步統計,本次災害已造成1人死亡8人失聯,天池、梨坪、舍書3個鄉鎮境內部分村民房屋倒塌或受損,通訊、電力中斷,縣鄉村道路多處塌方,灌溉水渠、人畜飲水管道不同程度受損,農作物不同程度受災。
  • 【財經早餐】2016.1.21星期四(英文版)
    7、證券時報消息,2015年1月1日至2016年1月19日,共有10家保險公司舉牌了31家上市公司,合計買入94.69億股,市值達1199億元。由於每年的年中和年末成為險企償債能力考核的重要時點,相信今年在這兩個時點也會是險資舉牌的密集期。
  • 「專家講專業」第五期:重金屬汙染場地健康風險評估 ——以南方某鉻鹽生產場地為例
    汙染物的致癌斜率因子(SF):指每天單位質量的某種致癌汙染物對人體單位體重可能產生的致癌風險程度(mg汙染物·kg-1體重·d-1)-1。參考劑量(RfD):指每天人體單位體重可容納的汙染物含量,在此含量內通常對人體健康不構成威脅 (mg汙染物·kg-1體重·d-1) 。
  • 如何更好識別短暫性腦缺血發作後卒中風險?
    那麼如何才能更好識別TIA後卒中發生的風險呢?目前,TIA發作分診的最佳評估是ASCD2得分。然而,該評分並不能準確區分處於高風險和低風險的TIA患者。日前,該研究團隊為了驗證CTIAS對急診TIA發作後卒中風險的評估準確性,開展了一項納入13個急診中心,共7607名TIA發作患者、歷時5年的研究。結果發表在最近的《英格蘭醫學雜誌》(BMJ)上。
  • 《自然綜述:心臟病學》中文版2017年第1期----第一部分
    結果發現,rs7178051(ADAMTS7 上遊區)的每一個 T 等位基因都可使從不吸菸個體的 CHD 風險降低 12%,而在吸菸者中僅可降低 5%。體外研究顯示,暴露於香菸提取物可誘導人冠狀動脈平滑肌細胞中的ADAMTS7 表達。研究人員表示:「抑制 ADAMTS7 有可能成為一種 CHD 新的、潛在的治療策略,尤其有益於吸菸者」。
  • 膽結石疾病和膽紅素水平與大腸癌風險有關嗎?
    膽結石疾病和膽紅素水平與大腸癌風險有關嗎?關於膽結石疾病和循環中膽紅素水平與結直腸癌(CRC)風險之間關係的流行病學研究結果也並不一致。為了解決可能的混淆和反向因果關係,近日,腫瘤學領域權威雜誌British Journal of Cancer上發表了一篇研究文章,研究人員使用孟德爾隨機化(MR)評估了這些潛在危險因素與CRC之間的關係。
  • 「輪班工作」男性一族,請注意食管癌風險!
    將於美國東部標準時間1月15~17日線上召開的ASCO GI 2021公布的一項薈萃分析,為我們提供了一定線索:輪班工作與男性食管癌風險增加相關。全球每年有超過57萬人被診斷為食道癌。國際癌症研究機構(International Agency for Research on cancer,IARC)認為,涉及晝夜節律紊亂的倒班工作可能是導致癌症的原因之一。