Metro Line 15 successfully passed the pre-operation safety assessment, and will start operation before this Spring Festival.
Shentong Metro Group said that Line 15 has successfully passed the initial pre-operation safety assessment and has the initial operating conditions for fully automatic operation. Before the trial operation is opened, further comprehensive system debugging and various drills will be carried out on the facilities and equipment of the whole line to ensure the trial operation before the Spring Festival (Lunar New Year).
Project metro line 15 starts from Zizhu High-tech Zone Station in Minhang District and ends at Gucun Park Station in Baoshan District. The line is about 42 kilometers long and has 30 underground stations, including 8 stations and the other 9 line to transfer. Lines form a transfer. See ↓
Attention:
Because of the difficulty of construction and the comprehensive impact of the epidemic situation, the construction period of Guilin Road Station needs to be appropriately extended, and it will not be opened this time.
Due to various factors such as the length of the station, the site and the relocation of the surrounding pipelines, the construction organization is extremely difficult and the process is very complicated. With the joint efforts of various construction units to catch up with the progress, firstly, the plan nodes such as the completion of the entire track and the commissioning of the trains were ensured. At present, the construction of the station still needs time, and the transfer to Guilin Road Station of Line 9 will be realized synchronously after the opening.
As the transfer channel between Loushanguan Road Station and Line 2 involves the transformation of the underground space of a commercial complex, a virtual transfer outside the station is temporarily implemented. After the transformation is completed, the same station transfer function of Line 2 and Line 15 can be realized.
At the same time, due to the adverse effects of the epidemic situation on the construction period of some station entrances and exits last year, all connected ground sidewalks have not been restored. The relevant construction units are making every effort to promote the construction work and strive to provide passengers with travel convenience as soon as possible. During this period, passengers can enter and exit the station through temporary access roads.
The "Tong Xue" line connects 09 university campuses in series, radiating multiple city sub-centers and science and technology parks Line 15 connects 9 universities with 10 campuses, which is a veritable university-to-university route (Shanghai Jiao Tong University Minhang Campus, East China Normal University Minhang Campus, East China University of Science and Technology Xuhui Campus, Shanghai Normal University Xuhui Campus, Shanghai University of Applied Sciences Xuhui Campus, Gubei Campus of Shanghai University of International Business and Economics, Xianxia Road Campus of Shanghai University of Engineering Science, North Central Campus of East China Normal University, Huxi Campus of Tongji University, Baoshan Campus of Shanghai University), 4 parks, 3 national science and technology parks; It connects Zhenru Sub-center, Changfeng Business District, South Railway Station, Caohejing Science and Technology Park, Zizhu High-tech Zone and other important areas, which will forcefully drive and support regional development; connect Shanghai West Railway Station and South Railway Station hubs, which is important for improving the comprehensive transportation hub. Supporting transportation plays an important role.
Source: Shanghai Release